Watch Contruent's latest ProcureWare webinar on demand.

  • Solutions
    • Back
    • Improve Planning for Project Success
    • Optimize Spend & Performance
    • Manage Contracts & Contractor Activity
    • Improve Visibility to Make Informed Decisions
    • Account for Change & Maximize Efficiency
  • Products
    • Back
    • Contruent Enterprise
      • Back
      • Contruent Enterprise
      • Procurement
        • Back
        • ProcureWare
        • Vendor Management
        • RFP Management & Bid Analysis
        • Contract Award
      • Estimate
        • Back
        • Estimate
        • QTO (2D, 3D, BIM)
        • Estimating
      • Engineering
        • Back
        • Contruent Engineering
        • Design Phase Controls
      • Cost Controls
        • Back
        • Contruent Cost
        • Budget Management (WBS/CBS)
        • Earned Value Management
        • Field Management
        • Cost Forecasting
        • Integrated Schedules
      • Contracts
        • Back
        • Contruent Contracts
        • Contracts and Commitments
        • POs & Invoices
        • Pay Requests & Progress Claims
        • Change Orders
      • Change Management
        • Back
        • Contruent Change Management
        • Trends & Change Orders
        • Approvals & Certified Audit Trail
      • Data Insights
        • Back
        • Contruent Data Insights
        • Executive Dashboards
        • Custom Reports
        • Business Intelligence
      • Integrations
  • Industries
    • Back
    • Mining
    • Oil & Gas
    • Power, Energy, & Renewables
    • Infrastructure
    • Transportation
    • Engineering & Construction
  • Roles
    • Back
    • Executives & Owners
    • Cost Engineers
    • Project Managers
    • Field Engineers
    • Procurement Managers
    • Estimators
  • Resources
    • Back
    • Content Hub
    • Events
    • Implementation
    • Customer Support
    • Product Announcements
  • About
    • Back
    • Why Contruent?
    • Company History
    • Leadership Team
    • Media + Press
    • Careers
    • Contact Us
  • Request a Demo

Case Study

Driving Cost and Schedule Accuracy for Clean Energy Megaprojects

About

A major U.S.-based energy company, serving millions of customers across multiple states, embarked on a high-stakes infrastructure project to deliver cleaner, more reliable energy while fostering regional economic growth. The initiative included the construction of two new nuclear reactors, marking the first such development in the U.S. in over three decades.

Industry
Energy & Power

Company size
5,000+

Headquarters
United States

ARES PRISM

Challenges

This groundbreaking clean energy project faced several challenges:

  • Escalating Costs: Construction costs exceeded initial estimates by over $2 billion.
  • Delays: Completion timelines were pushed back multiple times, creating uncertainty.
  • Inconsistent Processes: Disconnected systems and inaccurate data hindered visibility and decision-making.
  • Regulatory Oversight: Quality control issues led to increased regulatory scrutiny, adding further complexities.

Solution

To overcome these challenges, the company sought a scalable and integrated project management solution capable of:

  • Enhancing cost and schedule tracking while reducing project risk.
  • Providing real-time visibility into project status, trends, and forecasts across departments.
  • Seamlessly integrating with Oracle P6, Microsoft Excel, and ERP systems.
  • Connecting data across scheduling, cost, procurement, and field operations.
  • Standardizing estimating processes with audit trails to track and document changes.

The chosen solution addressed these needs while supporting the company’s increasingly complex megaproject portfolio.

Results

The implementation of a robust project management platform delivered significant results:

  • Improved Forecasting: Enhanced cost and schedule accuracy reduced project risk and provided better visibility into project health.
  • Increased Efficiency: Real-time dashboards and pre-built reports empowered teams to make data-driven decisions.
  • Proactive Contract Management: Streamlined workflows and mobile access enabled the company to handle contract changes effectively.
  • Simplified Operations: Contractor activities, RFP management, and bid analysis were streamlined, improving overall efficiency.

Download Case Study

“Contruent allows us to reduce risk and increase the accuracy of our spend and schedule forecasting leading to improved planning, budgeting and control to help us stay on-time and on-budget.”

Project Manager, North American Energy Company

Related Content

Case Study

Infrastructure Company Fine Tunes Cost Control Process Accelerating Project Delivery

Optimized cost controls & faster project launch empower a European...

Case Study

Accelerating Project Delivery with Fine-Tuned Cost Control Processes

Optimized cost controls & faster project launch empower a European...
logistics

Case Study

Transportation Leader Enhances Project Cost Reporting

Improved reporting accuracy & efficiency streamline cost management for...
ARES PRISM


Contruent HQ

55 Shuman Blvd Suite 200
Naperville, IL 60563

1-630-318-0444

Global Offices

  • United States
  • United Kingdom
  • Australia
  • Canada

About

  • About Contruent
  • Media/Press
  • Careers
  • FAQs
  • Contact Us

©2025 Contruent. All rights reserved. Privacy Statement.

  • Follow
  • Follow
  • Follow
  • Follow
